Computerworld

Microsoft envisions ultra-modular data centers

The software giant is experimenting with efficient designs that can be ramped up quickly when it needs capacity

In the years to come, Microsoft's data centers may not be huge buildings tightly packed with server racks, but rather rows of small, stand-alone IT units spread across acres and acres of cool, cheap land.

At the DatacenterDynamics conference in New York on Wednesday, Microsoft data center general manager Kevin Timmons outlined some prototype work his unit is doing to design its next generation of data centers, in collaboration with Microsoft Research.

His vision is radically different from most of what the company already has in place.

The company is field-testing something Timmons calls IT PACs, or IT preassembled components, which are small, self-contained units that are assembled off-site and can be linked together to build out an entire data center.

Microsoft, he said, is facing the same challenges as most data center operators. It needs the ability to ramp up capacity in short order, but would like to avoid the massive up-front costs and long lead times required to build out traditional data centers. Given this set of conditions, Microsoft's goal for building its next set of data centers is "ultra-modularity," Timmons said.

Instead of paying US$400 million or more up front to build a data center, Microsoft would prefer to purchase some land, build a sub-station and then populate the acreage with modular units of servers as demand grows.

"We want to view our data centers as more of a traditional manufacturing supply chain, instead of monolithic builds," he said. "It won't all be built on-site in one shot."

By going with this approach, Microsoft can cut the time it takes to ramp up new server capability in half, as well as reduce the costs of building out new data centers, Timmons predicted. "You don't have to commit to a $400 million data center and hope that demand shows up," he said.

Over the past few years Microsoft has been moving toward more modular designs, moving from purchasing individual servers to racks of servers to, most recently, entire containers filled with servers. Microsoft built out its past two data centers, located outside of Chicago and Dublin, using, in part, containers.

The new design takes this modularity concept even further.

The IT PACs are "not really containers in a traditional sense," Timmons said. "They are really integrated air-handling and IT units."

The units themselves could hold anywhere from one to 10,000 servers. The idea is that when the software giant requires more resources, it can have one of these IT PACs shipped to location and "plugged into the spine," which supplies the power and network connectivity to the data center.

Microsoft has built two proof-of-concept models so far. Its next data center, which the company will announce in a few months, will use some form of these IT PACs, Timmons said.

The units will be assembled entirely from commercially available components. A single person should be able to build a unit within four working days. The servers will be stacked in rows, sandwiched between air intake and output vents.

For cooling, ambient air can be sucked in one side, run through the servers and exhausted out the other, with some of the air recirculated to even the overall temperature of the unit. No mechanical cooling units will be used. Networking and power buses will run over the tops of the servers.

The construction materials rely heavily on steel and aluminium, both easily recyclable. The water requirements can be met by a single hose with residential levels of water pressure, he said.

The development team considered different sizes of containers, Timmons said, keeping an eye toward making the units easily shippable. They settled on a size that could contain 1,200 to 2,100 servers and draw between 400 and 600 kilowatts.

The units can be placed inside a large building, or when equipped with outer protective panels, reside out in the open.

One of the chief requirements of IT PACs, he admitted, is that they reside in an area where the ambient temperature is mild enough that it can provide sufficient cooling. Because of their highly portable nature, this should not be a problem, he said.

"If we're doing our job right in site election, square footage will be cheap for me. I want to find a place with lots of room to expand. I don't want to worry about a watts-per-square-foot problem. I'd like to worry about having enough acreage," he said. "We're doing a good job in site selection when we don't have to squeeze in 500 watts per square foot."

Due to their minimal use of mechanical cooling, Timmons estimated that the PUE ratio for its IT PACs would be 1.26 to 1.35, depending on the outside conditions. PUE, or power usage effectiveness, compares overall power supplied to the data center against the amount that actually reaches IT equipment.

A typical data center PUE is around 2.1, according to industry estimates.

If the IT PACs are ultimately pushed into production, Timmons said he hasn't fully decided if Microsoft will build them itself or contract them out. It would probably be a mix of the two, he predicted. "I know how much it costs to build one of these now," he said.